FER X decree 119: three rules to follow from 13 November to keep your incentive

Updated 18 November 2026. Sources: MASE and GSE publications and Italian trade press.

Since 13 November 2026 the FER X definitivo, Italy’s incentive scheme for mature renewables, has updated operating rules. The FER X decree 119, issued on 11 November by the Ministry of Environment and Energy Security (MASE), integrates and replaces the rules approved on 2 October and adds a new Part C. Part C covers how contracts with the GSE, the state energy services operator, are activated, how the incentivised energy is determined, payments, cumulation with other support and checks during the incentive period. For a solar project, three points can cost you the incentive: direct access up to 1 MW, the deadline to declare entry into operation, and the NZIA requirements.

The scheme totals 37.15 GW. Ten GW are reserved for direct access up to 1 MW, open until 31 December 2030 unless exhausted earlier, and 27.15 GW go to competitive procedures above 1 MW: 10 GW of solar, 16.50 GW of wind, 0.63 GW of hydro and 0.02 GW of gas from wastewater treatment. These figures are consistent across the trade summaries we checked, and the decree is listed on the MASE “Bandi e avvisi” page, where the full text should be read before any investment decision.

A short glossary for readers new to Italy: MASE is the energy and environment ministry, GSE manages incentives, GAUDÌ is the plant registry run by the grid operator Terna, and NZIA is the EU Net Zero Industry Act.

Direct access up to 1 MW: works start after 7 August and no splitting

Direct access applies to the cumulative nominal power up to 1 MW. Two calendar conditions apply: works must have started after 7 August 2026, and the plant must enter operation by 31 December 2030. Artificially splitting a project to stay under the threshold can lead to forfeiture and recovery of amounts already paid. Grid connection is the practical bottleneck for many developers.

Entry into operation: 90 days, and a price that can lapse

Entry into operation must be declared through the FER X definitivo portal within 90 days of entry into operation. Under direct access a late declaration is accepted within 180 days, but no award price is recognised for the period between entry into operation and receipt of the declaration. In competitive procedures a delay can mean losing the right to the incentive and the place in the ranking. Correct registration of the plant on GAUDÌ is required, and the summaries we reviewed do not state a specific deadline for it.

NZIA requirements apply from entry into operation

NZIA requirements must be met from the date of entry into operation, except the requirement on the ability to build the project on schedule. Checks cover, among other things, cybersecurity, sustainability and supply chain resilience. In practice, module and inverter choices should be made at the start of the project.

Rule What it says What you risk
Direct access Up to 1 MW, works started after 7 August 2026, in operation by 31 December 2030 Exclusion if the date conditions are not met
Splitting Not allowed if artificial, to stay under the threshold Forfeiture and recovery of amounts paid
Declaration of entry into operation 90 days; late declaration within 180 days under direct access No award price during the delay; in auctions, loss of the incentive
NZIA requirements Guaranteed from entry into operation, except ability to build on schedule Payments withheld, and checks

One gap remains: the summaries do not report payment amounts, percentages or timing under Part C. That requires the decree text.

Frequently asked questions

When do the new FER X operating rules apply

They have applied since 13 November 2026. Decree 119 of 11 November integrates and replaces the provisions of decree 93 of 2 October.

How long do I have to declare entry into operation

The standard deadline is 90 days. Under direct access a late declaration is possible within 180 days, without the award price for the uncovered period.

Can I split a project to stay under 1 MW

No, if the split is artificial. The decree provides for forfeiture and recovery of amounts paid.

Does decree 119 change the first auction dates

The summaries we reviewed do not report changes. The dates announced by the GSE for the offer window are a stated target, to be reconfirmed on the official call.

More from AssoSolare in English

More Italian regulation explained in English will appear in the AssoSolare English section. The magazine’s Italian archive of regulatory analysis is on the AssoSolare home page.

Institutional references

Decree 119 is published on the Italian Ministry of Environment and Energy Security “Bandi e avvisi” page. The operating rules, the FER X portal and the calls are on the GSE website, and plant registration runs through Terna and the GAUDÌ system.