Spanish capacity market 2026: contracts up to 15 years for new batteries, but no auction date yet

Updated 21 November 2026. Sources: Spanish Official State Gazette (BOE), Ministry for the Ecological Transition (MITECO), European Commission, and law firm analyses of Order TED/966/2026.

Spain has launched its first capacity market for the mainland electricity system. Order TED/966/2026 of 15 September 2026 was published in the Official State Gazette (BOE) on 17 September and entered into force the next day. Generators, storage operators, consumers and aggregators can sell firm capacity in centralized auctions, and new projects can hold contracts of up to 15 years. For battery developers the Spanish capacity market is the first dedicated revenue route in Spain, but the Order fixes the architecture and leaves the parameters that decide who wins to later documents.

How the Spanish capacity market works

The Order sets up three types of auction. In the main auction, delivery of the firm capacity starts within five years of the award, or up to nine years for a quota of new capacity (article 7.1.a). An adjustment auction covers delivery within twelve months, and annual transitional auctions bridge the years before the first main delivery. Auctions are sealed-bid and pay-as-bid, with prices in euros per MW per year, according to MITECO. Existing plants receive 12-month contracts, new generation and storage up to 15 years, and demand-side projects between one and ten years. Payment is made in twelve monthly instalments and is not indexed to inflation (articles 15.12 and 20.1).

Eligible participants are producers, storage owners, final consumers, demand aggregators including retailers and, new in the final text, aggregators of generation and storage. An individual installation needs at least 1 MW of firm power, while the units inside an aggregation must each be below 1 MW. Existing producers may not emit more than 550 g of fossil-fuel CO2 per kWh (article 11.c), and new projects without an operating permit must be renewable, storage or demand-side, as the law firm Cuatrecasas reads the text. The reliability standard rose to 1.5 hours of expected loss of load, from 0.94 hours in the draft. The cost is paid by electricity suppliers and direct market consumers through unit prices by tariff segment and time slot, according to MITECO.

What the Order leaves open

The firmness coefficients, which set how much of its nameplate power each technology can sell as firm capacity, are not in the Order. They are fixed in the resolution of the Secretary of State for Energy that calls each auction, on proposals from the system operator and from the regulator CNMC (article 10). The operating procedure that covers verification, guarantees and the method for these coefficients has not yet been approved. Without the coefficients and the volume of the first auctions, nobody can calculate what a given battery would earn. According to Aurora Energy Research, as reported by the trade site Energías Renovables, those two items will decide how stand-alone and hybrid storage compare with existing gas plants.

The Order sets no date for the first auction. One market adviser interviewed by Energía Estratégica expects it in 2027, between January and the end of March, which is a single source and not an official date. On 29 May 2026 the European Commission cleared the scheme under State aid rules, for up to 9 billion euros over ten years from May 2026. The Order allows delivery periods of up to 15 years, and Cuatrecasas flags that gap as a point to watch.

Summary: what is confirmed and what is open

Item What is confirmed Source
Scope Mainland (peninsular) system only; non-mainland systems are excluded Order TED/966/2026, BOE of 17 September 2026
Auctions Main (delivery within 5 years, up to 9 for a quota of new capacity), adjustment (within 12 months), annual transitional BOE, article 7 and preamble
Contract length Existing plants 12 months; new generation and storage up to 15 years; demand 1 to 10 years BOE, article 7.1.a
Indexation None; monthly payment is one twelfth of the awarded firm power times the awarded price BOE, articles 15.12 and 20.1
Reliability standard 1.5 hours (0.94 in the draft) BOE preamble; Energías Renovables
Firmness coefficients Not yet set; fixed in each auction call BOE, article 10
First auction date Not set; one adviser expects January to March 2027 Energía Estratégica
EU clearance Up to 9 billion euros over ten years from May 2026 European Commission, 29 May 2026

What to watch next

Three items decide whether Spanish capacity revenue can be financed: approval of the operating procedure, the first auction call with its firmness coefficients, and the date and volume of the first auction. Until then a financial model for a Spanish battery can include capacity income only as a scenario, and the project should be tested without it. For other markets, see our articles on Germany’s EEG 2027, on France and PPE3 and on the Italian FER X Decree 119.

FAQ

What is Spain’s capacity market

It is a centralized market created by Order TED/966/2026 in which generation, storage and demand sell firm capacity through auctions. It covers the mainland system only and entered into force on 18 September 2026.

Can batteries take part in the Spanish capacity market

Yes. Storage owners are eligible, with at least 1 MW of firm power per installation, and aggregators of storage can bid with units below 1 MW each. How much firm capacity a battery can sell depends on firmness coefficients that are not yet published.

How long are the contracts

Existing plants receive 12-month contracts. New generation and storage can receive up to 15 years, and demand-side projects between one and ten years.

When is the first auction

No date has been set. The Order leaves it to the calling resolution. One market adviser expects it between January and the end of March 2027, which is not an official date.

Who pays for the capacity

Electricity suppliers and direct market consumers, through unit prices that differ by tariff segment and time slot, according to MITECO.

Further reading from AssoSolare

The Global section of AssoSolare collects our English-language coverage of solar and storage rules in Europe. On support schemes in other countries, we looked at the German EEG 2027 draft law and at the French rooftop tariff and PPE3.

Official references

The full text of the Order is in the BOE of 17 September 2026, and the ministry explains the design in its MITECO press release of 16 September. For a legal reading of the changes against the draft, see the Cuatrecasas Legal Flash.